Crime & Safety

Observations of Oyster Creek Flood Audit Released

NRC had five observations during audit of Oyster Creek flood assessment process

The Nuclear Regulatory Commission has identified and communicated to Exelon Nuclear five observations after a review of its flood hazard walkdowns at the Oyster Creek Generating Station in Lacey.

The walkdowns are visual assessments at the plant conducted in response to the NRC's post-Fukushima flooding hazard re-evaluation requirements, said Neil Sheehan, NRC spokesman. Plant officials have described the observations as administrative, rather than substantive, issues.

From July 23 to 25, 2013, an NRC team reviewed the plant's own walkdown process which assess flood risks at the Lacey Township nuclear generating station.

In its audit of the plant's review process, the NRC made five observations, sent one to the NRC Resident Inspectors based at the plant for follow-up reviews and developed two potential requests for additional information, said Sheehan.

The observations "are neither findings nor violations; however, they will be used to inform the NRC staff assessment of the licensee's walkdown report," the audit, which was released this week, said.

The observations included a question of the flood height measurement on the roof of the plant's turbine building, indicating it is 23 feet, 6 inches. The listed height had "no physical meaning or relevance for a flood protection feature," according to the report.

"Although the discussions were helpful in understanding the thought process that went into the determination, the team believes that the physical meaning of APMs may not have been clearly understood," the audit said, referring to "available physical margin," which is represented by the "APM" acronym.

In another observation, the plant's operators referred to the turbine building doors as passive flood prevention features, though the doors themselves are non-watertight. Through discussions, the report said, the inspection team learned the designation referred to the door threshold rather than the doors themselves.

"This demonstrates that documentation of the relevant features in the walkdown form was not done properly," the audit said.

In its third observation, the inspection team learned that floor drain inspections were not typically performed using a company structural monitoring procedure. During a visual inspection, a 4-inch conduit at the plant was found "with extensive corrosion as well as very significant growth of stalactites," according to the audit.

The team also observed that APM was not calculated on several walkdown record forms, "particularly forms associated with penetration seals."

Finally, according to the audit, "in several instances, an evaluation was not performed on seals where the margin was small with potentially significant safety consequences."

The audit team found that flood protection features ocated on the southwest corner of the turbine building basement had water intrusion at about 40 drops per minute, and that a conduit containing cables that run to a second emergency diesel generator is located in a vault that could fill with water in the event that a drain clogs.

The NRC said in the audit that it will request additional information on APM calculations and, "moreover, the NRC staff may require additional information to clarify whether deficiencies were identified during the site walkdowns."

Find out what's happening in Laceywith free, real-time updates from Patch.

"Through Exelon’s procedures, items that are identified proactively by the station or by the NRC are addressed through a formal corrective action program," said Suzanne D'Ambrosio, plant spokeswoman. "The items noted in the NRC’s walkdown were documented in the station’s corrective action program, were mainly minor administrative issues, and are being addressed."


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

To request removal of your name from an arrest report, submit these required items to arrestreports@patch.com.